FAST-41 Projects With EPA Permits
EPA receives permit applications for projects covered by the Fixing America’s Surface Transportation Act - Title 41. This map shows the locations of FAST-41 projects with EPA permits across the U.S.
OCS = Outer Continental Shelf, NPDES = National Pollutant Discharge Elimination System, UIC = Underground Injection Control
Further information regarding project and permit status can be found on the table below or on the Permitting Dashboard for Federal Infrastructure Projects.
On the table below, the Milestone column uses milestones from the Permitting Dashboard (see graphic) to display the most recent milestone the permit has reached. “Schedule not yet established” is noted if federal agencies and project sponsors are working to develop a schedule, “pending” is noted if a schedule has been established but a milestone has not yet been reached and "paused" is noted if a project has not been cancelled but the permitting process cannot progress at this time.
EPA Region |
Project Name |
EPA Permit |
Milestone |
---|---|---|---|
Region 1 |
OCS permit |
||
OCS permit |
Schedule not yet established |
||
OCS permit |
Paused |
||
NPDES permit |
Paused |
||
OCS permit |
|||
NPDES permit |
|||
OCS permit |
|||
OCS permit |
|||
OCS permit |
|||
NPDES permit |
|||
Vineyard Northeast | OCS permit | NOI to apply for a permit submitted | |
NPDES permit | Permit Application Submitted | ||
Region 2 |
OCS permit |
||
NPDES permit |
|||
OCS permit |
|||
OCS permit |
|||
OCS permit |
|||
Vineyard Mid-Atlantic | OCS permit | Schedule not yet established | |
Region 3 |
NPDES permit |
Schedule not yet established |
|
OCS permit |
|||
Region 4 |
OCS permit |
||
OCS permit |
NOI = Notice of Intent